Project 8001, R63 C2 G69

Posted: Thu Jan 19, 2012 3:17 am
by SASinUtah
Interesting thing happened on the way to the forum............

This particular project has a preferred deadline of 1.64 days, roughly 40 hours. Yesterday, this project got up to 96% completion after 15 hours, then terminated, stating that the deadline had passed for this project. Any ideas?

Thom

Re: Project 8001, R63 C2 G69

Posted: Thu Jan 19, 2012 5:32 am
by bruce
Welcome to foldingforum.org, SASinUtah

Yes, the deadline got changed twice yesterday ... once incorrectly and then again to the proper value.

See this topic: viewtopic.php?f=19&t=20535

Re: Project 8001, R63 C2 G69

Posted: Thu Jan 19, 2012 5:51 pm
by SASinUtah
Thank you.